Our Cottage - Cottage Shell

Last Changed 7/5/2019

The first step for Our Cottage was to pour the foundation slab.

Retama Lot Build 3/19/19
A good sign the morning.  Concrete trucks lined up waiting to pour.

And the foundation slab pour had started.
Retama Lot Build Retama Lot Build Retama Lot Build
click on images to enlarge
click on images to enlarge
click on images to enlarge
Retama Lot Build Retama Lot Build Retama Lot Build
Retama Lot Build The garage floor was the last step.

We stayed back to kept out of the way of the workers.
click on images to enlarge
Retama Lot Build Retama Lot Build Retama Lot Build
click on images to enlarge
click on images to enlarge
click on images to enlarge

3/25/19
The excitement for today is the lumber for our future Cottage arrived.  The first of three shipments.

Retama Lot Build Retama Lot Build Retama Lot Build
click on images to enlarge
click on images to enlarge
click on images to enlarge
Retama Lot Build 3/26/19
The Cottage sewer system passed its test and so it was connected to the main sewer lines.
Retama Lot Build 3/26/19
The piles of lumber are starting to become Our Cottage.
Retama Lot Build
click on images to enlarge
click on images to enlarge
click on images to enlarge
Retama Lot Build Retama Lot Build Retama Lot Build
Retama Lot Build Retama Lot Build Retama Lot Build
click on images to enlarge
click on images to enlarge
click on images to enlarge

3/29/19
The roof is going up.

Retama Lot Build Retama Lot Build Retama Lot Build
Retama Lot Build 4/3/19
We know the construction is getting serious when the porta-potty arrives.
click on images to enlarge
Retama Lot Build Almost all the rafters are up and the sheathing is started.  Retama Lot Build
Retama Lot Build Retama Lot Build Retama Lot Build
click on images to enlarge
click on images to enlarge
click on images to enlarge
Retama Lot Build 4/4/19
Rafters are done.  The front of the Cottage has taken shape.

The roof sheathing and tar paper are almost done.
Retama Lot Build
click on images to enlarge
click on images to enlarge
click on images to enlarge
Retama Lot Build Retama Lot Build Retama Lot Build
Retama Lot Build Retama Lot Build Retama Lot Build
click on images to enlarge
click on images to enlarge
click on images to enlarge

4/11/19
Today the delivery of Autoclav Aerated Concrete (AAC), also known as Hebel, and the windows happened.

The AAC is two inches of light concrete that is used to cover the outside of the Cottage. This AAC layer has an R-Factor of 4 and provides a great base for the stucco covering.

Retama Lot Build These are sheets of the AAC sheathing. Retama Lot Build
click on images to enlarge
click on images to enlarge

The first step is applying the layer of Tyvec moisture barrier to the studs.

The shape of the front of the Cottage is becoming apparent.
Retama Lot Build Retama Lot Build Retama Lot Build
Retama Lot Build Retama Lot Build Retama Lot Build
click on images to enlarge
click on images to enlarge
click on images to enlarge
Retama Lot Build One our additions to the base plan was these transom windows located in the bathroom and hallway to the garage.

We had hoped to put the same windows in the kitchen but there wasn't wall space for the windows.  Those will be mounted in the side wall of the garage.
Retama Lot Build
Retama Lot Build The Cottage is taking a new feel as the walls are covered. Retama Lot Build
click on images to enlarge
click on images to enlarge
Retama Lot Build 4/12/19
Almost all the shingles were installed today.

Also, most of the AAC sheathing has been installed.

The Cottage is really looking like a house.
Retama Lot Build
Retama Lot Build Retama Lot Build Retama Lot Build
click on images to enlarge
click on images to enlarge
click on images to enlarge
Retama Lot Build 4/15/19
The AAC has been applied to the front columns..
Retama Lot Build
Retama Lot Build 4/15/19
The application of the stucco has started. 
Retama Lot Build
click on images to enlarge
click on images to enlarge
Retama Lot Build By the end of the day, about 2/3rds of one wall had the first coat.

Lots of works prepping the surface.
click on images to enlarge
click on images to enlarge
click on images to enlarge
Retama Lot Build 4/18/19
Almost all the AAC is installed. 

More of the walls have the primary stucco layer..
Retama Lot Build
click on images to enlarge
 
click on images to enlarge
Retama Lot Build 4/22/19
With the exception of the windows on the end of the garage and the one in the bathroom, all the AAC has been installed.
Retama Lot Build
Retama Lot Build Almost all the installed AAC has had the primary coat of stucco applied.
Retama Lot Build
click on images to enlarge
 
click on images to enlarge
Retama Lot Build 4/25/19
Finally the Bathroom transom windows has been installed.
Retama Lot Build The framing for the transom windows in the garage have been done and the windows are present to be installed. Retama Lot Build
click on images to enlarge
 
click on images to enlarge
Retama Lot Build The front of the Cottage is basically done. 

Waiting for the stone fascia to applied where the white areas are.
Retama Lot Build
Retama Lot Build The fascia stones have arrived.

The framing walk-thru was completed and we are ready for the foam insulation.
click on images to enlarge
 

5/1/19
Today the AAC was finished around the remaining four transom windows,  The new AAC was coated with the primer and then the whole cottage was covered with the second stage coat of the stucco.

Retama Lot Build Retama Lot Build Retama Lot Build
Retama Lot Build 5/2/19
Most of the stucco final coat has been applied. 

Big conduit pipe attached to end of building and run though a trough to where the electrical hookup will be.
Retama Lot Build
click on images to enlarge
click on images to enlarge
click on images to enlarge
Retama Lot Build
Waiting on the stone facade.
Retama Lot Build
Retama Lot Build 5/3/19
Painting of the exterior is done
Retama Lot Build
click on images to enlarge
click on images to enlarge
Retama Lot Build 5/3/19
The stone fascia has started
 
Retama Lot Build 5/7/19
The stone fascia was finished today.
click on images to enlarge
Retama Lot Build 5/8/19
The curb cutting machine is here cutting the curb for our drive access.  Not quite done.
Retama Lot Build
Retama Lot Build 5/9/19
The electrician came and installed the meter box and the power connection for the AC external unit.
Retama Lot Build
click on images to enlarge
click on images to enlarge
Retama Lot Build 5/13/19
The electrical conduit for the fiber optic internet was laid into the trench with the electrical power feed.

Then the trench was filled in.
Retama Lot Build
Retama Lot Build 5/15/19
The garage received its door today.
Retama Lot Build
click on images to enlarge
click on images to enlarge
Retama Lot Build 5/21/19
Real excitement today with these trenches.  They are for the electric service and we have been waiting.
Retama Lot Build
Retama Lot Build 5/24/19
A look from the cottage front.

You can almost see the base for the power transformer.
Retama Lot Build
click on images to enlarge
click on images to enlarge
Retama Lot Build Some of the exterior lights.
Retama Lot Build
Retama Lot Build 5/31/19
The driveway has been framed.

The house number has been installed.
Retama Lot Build
click on images to enlarge
click on images to enlarge
Retama Lot Build The electrical transformer that feeds our Cottage has been installed.
Retama Lot Build 6/10/19
The patio extension slab was poured today..
click on images to enlarge
Retama Lot Build The driveway has been poured

The driveway from the garage.
Retama Lot Build
Retama Lot Build 6/18/19
A really big deal, the electric meter has been installed after a long wait.  Now many other installations can be done.
click on images to enlarge
Retama Lot Build The driveway has been poured

The driveway from the garage.
Retama Lot Build
Retama Lot Build 6/22/19
The drip irrigation is being laid.
click on images to enlarge
Retama Lot Build The gas line feed has been laid waiting for the meter.
Retama Lot Build The interface box for the fiber option internet connection has been installed.
click on images to enlarge
Retama Lot Build 7/5/19
The sod has been laid. Between the high heat and heavy rains, the grass looks a little weak.

The grass is already looking better with watering.
Retama Lot Build
Retama Lot Build Retama Lot Build Retama Lot Build
click on images to enlarge
click on images to enlarge
click on images to enlarge
Retama Lot Build The exterior is about done..
Retama Lot Build Retama Lot Build Retama Lot Build
click on images to enlarge
click on images to enlarge
click on images to enlarge

Disclaimer: The information in this site is a collection of data we derived from the vendors and from our personal experiences.  This information is meant as a learning guide for you to  make your own decisions  Best practices and code should always be followed.  The recommendations we make are from our personal experiences and we do not receive any compensation for those recommendations.